A "Milestone" in your project can be designated in one of two ways:

  1. In the New Task or Edit Task dialog, click on the "Advanced" tab, then select the "Milestone" checkbox.
  2. In the Task list view, right-click on the column header, choose "Add Column" then select "Milestone." You can then select the checkbox in this column.
                                     Milestone.png
 

The Gantt chart will show this  diamond graphic to indicate the milestone. 

                                            Milestone_2.png


Additionally, when you are in the Projects list (under the "Home" tab), your Milestone will display in the Gantt chart. You can mouse over the milestone in this view to see the name of the task it represents.